6/3/2016 

We finally installed the Daytona Beach buoy today just off the Sunglow Pier.  Enjoy!

 

6/12/2016

Unfortunately we lost contact with the newly installed buoy.  We are not sure what the issue is but we are aware and will be working on it as fast we can.  We apologize for any inconvenience and thanks for your patience.

 

6/17/2016

We have built and tested a new transmitter which we will swap out with the current one during our onsite troubleshooting.  We anticipate getting out out to this buoy sometime in the next week or two weather permitting.  The current forecast out to 6/21 is not conducive for field operations, however we will closely monitor current conditions to see if the forecast pans out.  Again, thanks for your patience.

10/7/2016

The Daytona Beach buoy is down due to Hurricane Matthew.  This buoy will be re-deployed when funds become available to build a replacement buoy.  Stay tuned for updates.

11/13/2016

The Daytona Beach buoy is back online.  We built a new buoy over the last few weeks and re-deployed it on 11/12/2016.  First we recovered the remains of the previous buoy which turned out to be everything from the flotation section on down.  This confirms that our theory of it's demise was correct, which was that the buoy got struck by surface debris most likely from the Sun Glow Pier that broke away.  While it was not a surprise that the wavegage survived it was a huge surprise that the transmitter did.  The transmitter housing is made of clear polycarbonate tubing and is waterproof to at least 100 ft but once the buoy broke apart it was no longer protected from the elements and was rolling around on the sea floor with the rest of the remains.

3/30/2017

The Daytona Beach buoy has been down for about a month now.  The cable took a hit during a big wave event in December and finally gave way in late February.  We were set to replace the cable but then saw the antenna mast had been broken as well requiring us to bring the whole buoy back to the shop for repairs.  We are about 2-4 weeks away from replacing the buoy once it has been repaired and we get good weather for re-deployment.

 

4/2/2017

The Daytona Beach buoy has been temporarily repaired thanks to the efforts of Chris Dembinsky who went out and secured the antenna mast so that it points to the sky instead of in the water.  A more permanent repair or replacement will be performed in the next 1-3 weeks.  So our initial thought that the cable had been compromised was wrong and it seems it was just the antenna mast all along.

4/26/2017

We are still waiting for a good weather window to get out to this buoy and do a more permanent fix to keep the data flowing more reliably.